Early december 2006 some 110 tonne concrete beams had to be placed over a highway in Eindhoven.
The main problem was that the highway should be closed as short as possible. The solution was to place both cranes right next allongside the road. Only during lifting and placing of the beams the road was closed some minutes by the police.
Because the AC 700 had another job Nederhoff was called if they could come with their AC 650.
Both the AC 650 from Nederhoff as Sarens Netherlands were fitted with 160 tonne counterweight and SL.
One of the trucks which brought the concrete beams. Many more projects like this have to take place this and next year near Eindhoven.